Tamazunchale gas pipeline project.

sTEEP TERRAIN

Project description & Scope of Work

The Tamazunchale gas pipeline needed to overcome a very steep section in the province Hidalgo. It was a special point, where there route needed to overpass not only a over 70° steep slope, but at the same time rocky terrain and make horizontal bend.

LCS provided a cable crane system with a payload of 6 tons to carry construction material as well as pipes into the very steep slope. The crane system ran over 800 m crossing very rocky terrain. Approximately at half way, after 400m, the crane system made a horizontal bend to follow the pipeline’s track. This was exactly at the most inclinated point of the pipeline route.

LCS was mainly responsible for the transportation system – means the cranes. The cable crane was used to transport all needed material – machinery, equipment, pipes, padding material etc.

Project Info

LocationMexico
Project OwnerTransCanada
CustomerGDI SICIM
Year2013-2014
Duration7 months
Size of pipe36"
Type of pipelineGas pipeline

Method

Cable Crane system for transportation and laying of pipes, with a total length of 800 m and a payload of 6 tons. The installation included a horizontal.

The crane system was used to transport 800 m of pipes, construction equipment, blasting and coating equipment as well as backfilling material.

Special Point description:

  • Length: 800m
  • Slope: over 70°+
  • Surface: Very rocky terrain
  • horizontal bend at the steepest point of the pipeline route

Project Gallery

“Very rocky an very steep terrain was overcome by mounting a powerful cable crane system.”

Complete pipeline construction in Asia

LCS was in charge of the complete construction service including all construction phases of an onshore pipeline in Myanmar.

Visit the Zawtika II project